Status of the HuCaB construction project


    Pouring the building’s foundation (August 2024):


    The excavation is complete; the shell construction phase is set to begin (July 2024):


    The crane arrives onsite (June 2024):


    Excavation begins (Mar. 2024):


    The large drill arrives onsite (Mar. 2024):


    The underground water storage tank is installed in front of GEMI; this water store will be used for plant irrigation (Feb. 2024):


    The cleared construction site (Jan. 2024):


    End of demolition process (Dec. 2023):




    Start of demolition process (Nov. 2023):


    Internal view of the annex during demolition (Nov. 2023)


    Preparations (Oct. 2023):


    Demolition: Begin October 2023
    Reconstruction of outdated annexes and demolition; the old clinic building is retained and continues to be used during the construction phase.