Status of the HuCaB construction project
Begin October 2023 Reconstruction of outdated annexes and demolition; the old clinic building is retained and continues to be used during the construction phase.Shell construction (since September 2024)
Pouring the building’s foundation (August 2024)
The excavation is complete; the shell construction phase is set to begin (July 2024)
The crane arrives onsite (June 2024)
Status of the excavation work - preparations for the arrival of the crane (May 2024)
Excavation begins (Mar. 2024)
The large drill arrives onsite (Mar. 2024)
The underground water storage tank is installed in front of GEMI; this water store will be used for plant irrigation (Feb. 2024)
The cleared construction site (Jan. 2024)
End of demolition process (Dec. 2023)
Start of demolition process (Nov. 2023)
Internal view of the annex during demolition (Nov. 2023)
Vorbereitung der Rücksanierung (Okt 2023)
Preparations (Oct. 2023)